Question: Assume for the following problems that work continues during weekends. a. A task is planned to start on April 30 and takes 20 days to

Assume for the following problems that work continues during weekends.

a. A task is planned to start on April 30 and takes 20 days to complete. The actual start date is May 3. After 4 days of work, the supervisor estimates that the task is 25 percent completed.

If the work rate stays the same, what is the forecast date of completion?

b. Task C has two immediate predecessors, Tasks A and B. Task A is planned to take 5 days to complete; Task B is planned to take 10 days. The early start time for both tasks is August 1. The actual start dates for Tasks A and B are August 2 and August 1, respectively.

At the end of August 4, Task A is assessed to be 20 percent completed and Task B 30 percent completed. What is the expected early start time for Task C?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!