Baselines, once established, identify: A. What the customer and contractor agree to B. What the sponsor and

Question:

Baselines, once established, identify:
A. What the customer and contractor agree to
B. What the sponsor and the customer agree to
C. What the customer wants done but not necessarily what the project manager plans to do
D. What the project manager plans on doing but not necessarily what the customer has asked for