Question: Basic Gantt Plan The simple Gantt chart below contains three activities. PVs for each activity are shown in bold font on each bar. Total completion

Basic Gantt Plan The simple Gantt chart below contains three activities. PVs for each activity are shown in bold font on each bar. Total completion estimates are shown as a percentage. Time period 2 is the status point. The accounting system has collected ACs for the three activities as 6, 12, and 6, respectively. Compute the EV parameters for this model. What is your prediction for cost and time completion of this project?

Task C B A 100% 5 30% 10 20% 1 2 Time

unit 3

Task C B A 100% 5 30% 10 20% 1 2 Time unit 3