Consider the following project information. The total budget is $36,000 and is expected to last six months.
Question:
Consider the following project information. The total budget is $36,000 and is expected to last six months. After four months, you have calculated the following information about the project:
PV = $29,000 EV = $30,500 AC = $28,000 Based on this information, calculate the SPI and CPI.
What is the estimated time and cost to completion? What does this information tell you about the project?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9781292269146
5th Global Edition
Authors: Jeffrey K.Pinto
Question Posted: