Consider the following project information. The total budget is $36,000 and is expected to last six months.

Question:

Consider the following project information. The total budget is $36,000 and is expected to last six months. After four months, you have calculated the following information about the project:

PV = $29,000 EV = $30,500 AC = $28,000 Based on this information, calculate the SPI and CPI.

What is the estimated time and cost to completion? What does this information tell you about the project?