During project closeout, you are required to attend to all these additional activities except: a. Apply appropriate

Question:

During project closeout, you are required to attend to all these additional activities except:

a. Apply appropriate updates to all organizational processes

b. Archive relevant project documentation

c. Retain project resources into the foreseeable future as a precaution

d. Close out procurement activities