fixed-price contract is typically sought by the project manager from the customer's organization when: A. The risk
Question:
fixed-price contract is typically sought by the project manager from the customer's organization when:
A. The risk and consequences associated with the A A contracted task are large and the customer wishes to transfer the risk.
B. The project manager's company is proficient at dealing with the contracted activities.
C. Neither the contractor nor the project manager understand the scope of the task.
D. The project manager's company has excess production capacity.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9781119805373
13th Edition
Authors: Harold Kerzner
Question Posted: