In which type of contract arrangement is the contractor least likely to want to control costs? A. Cost plus percentage

Question:

In which type of contract arrangement is the contractor least likely to want to control costs?
A. Cost plus percentage of cost
B. Firm-fixed price
C. Time and materials
D. Purchase order