Question: J. Smith (Project Manager for Print Software Pty Ltd) wants you to prepare a project network. Calculate the early, late and slack activity times. Determine
J. Smith (Project Manager for Print Software Pty Ltd) wants you to prepare a project network. Calculate the early, late and slack activity times. Determine the planned project duration and identify the critical path. His assistant has collected the following information for the Colour Printer Driver's Software Project:
| ID | Description | Predecessor | Time |
|---|---|---|---|
| A | External specifications | None | 8 |
| B | Review design features | A | 2 |
| C | Document new features | A | 3 |
| D | Write software | A | 60 |
| E | Program and test | B | 60 |
| F | Edit and publish notes | C | 2 |
| G | Review manual | D | 2 |
| H | Alpha site | E, F | 20 |
| I | Print manual | G | 10 |
| J | Beta site | H, I | 10 |
| K | Manufacture | J | 12 |
| L | Release and ship | K | 3 |
Step by Step Solution
3.50 Rating (150 Votes )
There are 3 Steps involved in it
planned project duration is 116 da... View full answer