Question: One of your primary concerns with the project scope is that the stakeholders may add requirements once the project is in motion. Why should the
One of your primary concerns with the project scope is that the stakeholders may add requirements once the project is in motion. Why should the project scope be guarded against even simple additions?
A. It adds team members to the project.
B. It distracts the team members from the project.
C. Additions, even simple ones, can greatly impact the success of a project.
D. Additions, even simple ones, must be approved through the project sponsor.