Question: One of your primary concerns with the project scope is that the stakeholders may add requirements once the project is in motion. Why should the

One of your primary concerns with the project scope is that the stakeholders may add requirements once the project is in motion. Why should the project scope be guarded against even simple additions?

A. It adds team members to the project.

B. It distracts the team members from the project.

C. Additions, even simple ones, can greatly impact the success of a project.

D. Additions, even simple ones, must be approved through the project sponsor.

Step by Step Solution

3.45 Rating (145 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!