Question: Project management maturity is strongly correlated with more predictable project schedule and cost performance. More mature companies have a schedule performance index (SPI) variation of

Project management maturity is strongly correlated with more predictable project schedule and cost performance. More mature companies have a schedule performance index (SPI) variation of 0.08 and a cost performance index (CPI) variation of 0.11. Less mature companies have indexes of 0.16 for SPI and CPI. For a

$10 million project, this translates into a $1.6 million cost variation.