Question: State whether True or False: a. During resource levelling exercise, the critical activities are given priority for resource allocation. b. Time-cost trade-off analysis in CPM

State whether True or False:

a. During resource levelling exercise, the critical activities are given priority for resource allocation.

b. Time-cost trade-off analysis in CPM tries to optimize the project duration to minimize the total project cost.

c. An activity with the highest cost slope is to be considered first for crashing.

d. When there is more than one critical path in a network, crashing an activity on any one path will reduce the project duration.

e. Resource levelling exercise uses activity floats to reschedule activities, without delaying project completion.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!