Question: The original bidding process favored the lowest project construction bids using a fixed price contract. What are the advantages and disadvantages to the Indian government
The original bidding process favored the lowest project construction bids using a “fixed price” contract. What are the advantages and disadvantages to the Indian government from using this type of bidding process? How did it contribute to gross underbids and successive cost escalations?
Step by Step Solution
3.40 Rating (166 Votes )
There are 3 Steps involved in it
Fixed price contracts do not allow for addons and assume that the final price is that which was bid ... View full answer