Question: The project manager always involves the team in the creation of the work breakdown structure. What is the most significant benefit derived from this approach?
The project manager always involves the team in the creation of the work breakdown structure. What is the most significant benefit derived from this approach?
a. Generation of a more accurate schedule
b. Establishment of the project manager’s authority
c. Generation of a more accurate budget
d. Buy-in from the team doing the work
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
The most significant benefit of involving the team in creating the work breakdown structure WBS is d ... View full answer