Question: The project manager identifies 20 tasks needed to complete her project. She has four project team members available to assign to these activities. The process

The project manager identifies 20 tasks needed to complete her project. She has four project team members available to assign to these activities. The process of assigning personnel to project activities is known as:

a. Resource leveling

b. Resource loading

c. Finding the critical path

d. Creating a Work Breakdown Structure (WBS)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

bThe act of assigning ... View full answer