Question: The project manager identifies 20 tasks needed to complete her project. She has four project team members available to assign to these activities. The process
The project manager identifies 20 tasks needed to complete her project. She has four project team members available to assign to these activities. The process of assigning personnel to project activities is known as:
a. Resource leveling
b. Resource loading
c. Finding the critical path
d. Creating a Work Breakdown Structure (WBS)
Step by Step Solution
There are 3 Steps involved in it
bThe act of assigning ... View full answer