Which of the following circumstances would require the creation of a lag relationship in a network diagram?

Question:

Which of the following circumstances would require the creation of a lag relationship in a network diagram?

a. The critical path

b. The insertion of a dummy variable into a network diagram

c. A delay after painting a room to allow for the paint to dry before beginning to carpet the room’s floor

d. An early finish relationship between two activities

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: