Question: Which of the following generally cannot be validated using a work breakdown structure? A. Schedule control B. Cost control C. Quality control D. Risk management
Which of the following generally cannot be validated using a work breakdown structure?
A. Schedule control
B. Cost control
C. Quality control
D. Risk management
Using the work breakdown structure (WBS) shown below (numbers in parentheses show the dollar value for a particular element):


1.00.00 1.1.0 ($25K) 1.1.1 1.1.2 ($12K) 1.2.0 1.2.1 ($16K) 1.2.2.0