Question: 10. Your current project has both value and risks to consider. In what order would the risk compared to value be placed to have a

10. Your current project has both value and risks to consider. In what order would the risk compared to value be placed to have a completed risk-adjusted backlog?

A. Highest-impact risk first B. Highest-value items first C. A review of both risk and value would be considered, and the one with the highest financial impact would be chosen to be accomplished first.

D. A review of both risk and value would be considered, and the one with the lowest financial impact would be chosen to be accomplished first.