Question: 169. A project team has just completed the final work packages for a project. The project manager needs to find the final CPI for the

169. A project team has just completed the final work packages for a project. The project manager needs to find the final CPI for the project.

The BAC was $250,000, but the actual costs came in at $286,000.

What’s the final CPI?

A. .87 B. $286,000 C. -$36,000 D. The earned value information is needed to answer this question.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management The Managerial Process Questions!