Question: 22. In your organization, all project procurement must pass through a centralized contracting office. All correspondence between you and the vendors must be recorded and

22. In your organization, all project procurement must pass through a centralized contracting office. All correspondence between you and the vendors must be recorded and stored as part of the procurement records management system. These rules also provide instructions for the project’s procurement document packages from procurement planning through contract closure. Which one of the following is true about procurement document packages?

A. They offer no room for bidders to suggest changes.

B. They ensure the receipt of complete proposals.

C. They inform the performing organization why the bid is being created.

D. The project manager creates and selects the bid.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management The Managerial Process Questions!