Question: 23. As a project manager, you must use multiple types of communication with stakeholders to keep them engaged with the project work. All of the
23. As a project manager, you must use multiple types of communication with stakeholders to keep them engaged with the project work. All of the following are types of communications that are related to stakeholder engagement except for which one?
A. Pull communications B. Push communications C. Interactive communications D. Ad hoc communications