Question: 24. Mari, the project manager, has allotted two weeks for travel delays within her project. She has no proof that travel days will happen. This

24. Mari, the project manager, has allotted two weeks for travel delays within her project. She has no proof that travel days will happen. This is an example of what?

A. Change control B. Constraint C. Ineffective project management D. Assumption