Question: 24. Mari, the project manager, has allotted two weeks for travel delays within her project. She has no proof that travel days will happen. This
24. Mari, the project manager, has allotted two weeks for travel delays within her project. She has no proof that travel days will happen. This is an example of what?
A. Change control B. Constraint C. Ineffective project management D. Assumption
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
