Question: 25. The Close Phase or Project process is used to close a contract. All the following procurement documentation is collected except: A. Payment records B.
25. The Close Phase or Project process is used to close a contract. All the following procurement documentation is collected except:
A. Payment records B. Information on cost performance C. Inspection results D. Buyer’s meeting minutes