Question: 36. The project you are managing has a problem that requires the contract with a seller to be modified. The alteration to the contract is

36. The project you are managing has a problem that requires the contract with a seller to be modified. The alteration to the contract is in accordance with the change control terms of the contract and project. The best time to make this change to the contract is:

A. Never; the contract cannot be modified at any time B. At any time, regardless of the response from the seller C. At any time prior to the contract being awarded to the seller D. At any time prior to contract closure by mutual consent