Question: 43. You have been developing a scope statement for a project you have been given authority to manage. During this process, you came across areas
43. You have been developing a scope statement for a project you have been given authority to manage. During this process, you came across areas of technical details that you were not familiar with.
Which of the following would you use to help clarify the related issues and their impact on the project scope?
A. Experienced managers B. Special interest groups C. Expert judgment D. Similar project plans