Question: 51. From your experience with other projects, you know that the Control Schedule process results in people focusing on slippage and many times forgetting to

51. From your experience with other projects, you know that the Control Schedule process results in people focusing on slippage and many times forgetting to look for:

A. Lag B. Slack C. Opportunities D. Critical tasks