Question: 52. Risk analysis is an iterative process within any project. It sometimes helps to classify and break down the risk events to provide a deeper
52. Risk analysis is an iterative process within any project. It sometimes helps to classify and break down the risk events to provide a deeper understanding of them. Which structure lists the categories and subcategories for risks within a project?
A. The work breakdown structure B. The organizational breakdown structure C. The risk breakdown structure D. The bill of materials structure