Question: 6. You have compiled your performance reports and are about to have a meeting with your sponsor. Your current performance information shows which of the

6. You have compiled your performance reports and are about to have a meeting with your sponsor. Your current performance information shows which of the following:

EV = 30,000; PV = 32,000; AC = 28,000 What will you be reporting to your sponsor about the project schedule and budget?

Behind schedule and over budget Ahead of schedule and under budget Behind schedule and right on target for the budget Behind schedule and under budget