Question: 76. Your program manager says you should use earned value management (EVM) on your drug project. You decide to implement the milestone method of tracking
76. Your program manager says you should use earned value management (EVM) on your drug project. You decide to implement the milestone method of tracking project progress. This means that:
A. You can also use other methods such as CCM and CPM B. Stakeholders must be kept fully informed to establish realistic expectations C. You will not need to use EAC, ETC, or BAC D. You will need to consider dependency types and integration