Question: 78. A section of your project plan lists methods and technologies to be used to convey memoranda, email, press releases, and how frequently these should

78. A section of your project plan lists methods and technologies to be used to convey memoranda, email, press releases, and how frequently these should be used. The document that defines these is called a(n):

A. Communications management plan B. Organizational assets C. Communications technology D. Project management plan