Question: 81. During the initial project team meeting, the project manager and the project team established ground rules for how project team meetings would operate. Tina,

81. During the initial project team meeting, the project manager and the project team established ground rules for how project team meetings would operate. Tina, a project team member, is not obeying the project rules. Who has the responsibility to enforce the rules?

A. The project manager B. The project sponsor C. The project team D. The human resources department