Question: 89. During the Plan Procurement Management process for a project, you decide whether a product or service can be produced by the project team or

89. During the Plan Procurement Management process for a project, you decide whether a product or service can be produced by the project team or instead should be purchased. This decision-making process is called:

A. Procurement management B. Expert judgment C. Risk management D. Make-or-buy analysis