Question: A project deliverable is completed but does not meet the specified quality standards. What should the project manager do? a) Ignore the issue and continue
A project deliverable is completed but does not meet the specified quality standards. What should the project manager do?
a) Ignore the issue and continue with the project
b) Document the issue and take corrective actions if necessary
c) Inform the project sponsor and stakeholders
d) Request additional resources
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock