Question: A project manager is completing a project for another organization and is currently completing risk planning in order to determine which risks demand actions in
A project manager is completing a project for another organization and is currently completing risk planning in order to determine which risks demand actions in the project. Which one of the following must be considered when planning to take actions regarding the project risks?
A. Herzberg’s Theory of Motivation B. The Utility method C. The negative risk event value D. The organizational structure