Question: A project manager needs to add a new feature to the project deliverable. What process should they follow? a) Direct and Manage Project Work b)

A project manager needs to add a new feature to the project deliverable. What process should they follow?

a) Direct and Manage Project Work

b) Perform Integrated Change Control

c) Develop Project Management Plan

d) Validate Scope