Question: During a project review, a stakeholder requests an additional milestone. What should the project manager do? a) Implement the milestone immediately b) Evaluate the impact
During a project review, a stakeholder requests an additional milestone. What should the project manager do?
a) Implement the milestone immediately
b) Evaluate the impact of the milestone and process it through the change control system
c) Reject the milestone to avoid schedule changes
d) Update the project schedule