Question: During project execution, a task is found to be running ahead of schedule. What should the project manager do? a) Ignore the issue and continue
During project execution, a task is found to be running ahead of schedule. What should the project manager do?
a) Ignore the issue and continue with the project
b) Document the issue and update the project schedule
c) Inform the project sponsor and stakeholders
d) Request additional resources