Question: For the inter-dependencies and time estimates given in Table E11.2, determine the probability of completing the project by the end of day 40. Table E11.3

For the inter-dependencies and time estimates given in Table E11.2, determine the probability of completing the project by the end of day 40.


Table E11.3 Time durations and inter-dependencies between various activities Activities ABC Depends

Table E11.3 Time durations and inter-dependencies between various activities Activities ABC Depends upon Time durations (days) d 112 2 D A, B 3 E B 3 F B, C G H I J D, F D, F F E, H K G, J. I SI3SIST 1 5 4 d 8 3 3 Jxmm54267279 d 5 15 9 9