Question: Henry has been tasked to create a salience model for his project. This model defines three characteristics for project stakeholders. Which one of the following
Henry has been tasked to create a salience model for his project. This model defines three characteristics for project stakeholders. Which one of the following is NOT one of the three characteristics of the stakeholders mapped in the salience model?
A. Power B. Urgency C. Legitimacy D. Influence