Question: How should a project manager handle a significant change request that impacts the project scope? a) Approve the change immediately b) Reject the change request
How should a project manager handle a significant change request that impacts the project scope?
a) Approve the change immediately
b) Reject the change request to avoid scope creep
c) Submit the change request to the change control board (CCB) for evaluation
d) Implement the change and inform stakeholders later