Question: In a software development team, the average throughput is eight completed user stories per week. The average cycle time for a user story is four


In a software development team, the average throughput is eight completed user stories per week. The average cycle time for a user story is four weeks. Based on Little’s Law, what is the average work in process (WIP) in the system?

A. 2 user stories B. 16 user stories C. 32 user stories D. 64 user stories

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts