Question: In a software development team, the average throughput is eight completed user stories per week. The average cycle time for a user story is four
In a software development team, the average throughput is eight completed user stories per week. The average cycle time for a user story is four weeks. Based on Little’s Law, what is the average work in process (WIP) in the system?
A. 2 user stories B. 16 user stories C. 32 user stories D. 64 user stories