Question: In most projects, change is inevitable. Changes must be considered for their impact on the project as a whole, documented, and tracked throughout the entire
In most projects, change is inevitable. Changes must be considered for their impact on the project as a whole, documented, and tracked throughout the entire project. Which system would track how project deliverables are controlled, changed, and approved?
A. The change control system B. The project management information system C. The change management system D. The scope management system