Question: In your project management plan development, youll need several inputs. Of the following, which one is an input to project plan development? A. Assumptions B.

In your project management plan development, you’ll need several inputs. Of the following, which one is an input to project plan development?

A. Assumptions B. Outputs from other project management processes C. Earned value management D. Business needs