Question: Scope validation must be documented and communicated with the project team and project stakeholders to ensure the timing and scheduling of the event. When does
Scope validation must be documented and communicated with the project team and project stakeholders to ensure the timing and scheduling of the event. When does scope validation happen?
A. Only at the end of the project B. At the end of each project phase C. With each deliverable D. As the customer sees fit