Question: The framing activity cannot begin until the concrete has cured for 36 hours. The time between the concrete activity and the framing activity is best
The framing activity cannot begin until the concrete has cured for 36 hours. The time between the concrete activity and the framing activity is best described as which one of the following?
A. Hard logic B. Lag time C. Lead time D. Finish-to-start relationship
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts