Question: The project manager and a quality engineer have completed a sixmonth analysis of production in a manufacturers environment. The quality engineer now wants to plot

The project manager and a quality engineer have completed a sixmonth analysis of production in a manufacturer’s environment. The quality engineer now wants to plot out the results to identify trends.

Which one of the following is the chart or diagram that will best satisfy the request?

A. A Pareto chart B. An Ishikawa diagram C. A control chart D. A flowchart