Question: What are the three basic ways to gather information on project status? (a) SV, CV, and CPI (b) Stakeholder management plan, communications management plan, and
What are the three basic ways to gather information on project status?
(a) SV, CV, and CPI
(b) Stakeholder management plan, communications management plan, and responsibility assignment matrix
(c) Test results, customer feedback, and sponsor reaction
(d) Meetings, reports, and inspections