Question: What is the best approach for handling scope changes during a project? a) Reject all scope changes to avoid scope creep b) Evaluate the impact

What is the best approach for handling scope changes during a project?

a) Reject all scope changes to avoid scope creep

b) Evaluate the impact of the changes and process them through the change control system

c) Implement the changes immediately to keep stakeholders happy

d) Ignore the changes and continue with the project