Question: What role does the critical path method play in Schedule Management? a) It identifies the total cost of the project b) It determines the sequence
What role does the critical path method play in Schedule Management?
a) It identifies the total cost of the project
b) It determines the sequence of activities that directly affect the project completion date
c) It defines the project scope
d) It manages project risks