Question: What should a project manager do if they discover that additional procurements are needed to meet project objectives? a) Add the procurements to the procurement
What should a project manager do if they discover that additional procurements are needed to meet project objectives?
a) Add the procurements to the procurement management plan immediately
b) Submit a change request through the Perform Integrated Change Control process
c) Reject the additional procurements to avoid changes
d) Update the project charter