Question: What should a project manager do if they identify a misalignment between project activities and business objectives? a) Continue with the project as planned b)

What should a project manager do if they identify a misalignment between project activities and business objectives?

a) Continue with the project as planned

b) Ignore the misalignment

c) Realign project activities with business objectives through the change control process

d) Escalate the issue to the project team